Posted by: shirish February 13, 2008
Login in to Rate this Post:
0
?
from Spotlight
KARNALI PEOPLE ROBBED OF VAST WATER WEALTH
Suicidal Upper Karnali Hydropower Deal
AB Thapa
AB Thapa |
Several dailies including THE KATHMANDU POST of January 25, 2008 reported horrifying news that the Ministry of Water Resources has signed a MoU with a GMR team to finalize the deal to allow latter to implement the 300 MW Upper Karnali Project. The MoU to implement the 300 MW Upper Karnali Hydropower is going to be a suicidal deal. The Karnali people will be robbed of the great opportunity to benefit from their vast water wealth as a result of the decision to implement the 300 MW Upper Karnali project.
The proposed 300 MW Upper Karnali project can be implemented only at the cost of sacrificing the 4180 MW Upper Karnali Storage project According to the pre-feasibility study report the 300 MW Upper Karnali project and the 4180 MW Upper Karnali storage project are mutually exclusive. The 4180 MW Upper Karnali project is the most attractive hydropower among the projects identified so far in Nepal. It far excels even the highly attractive 10,800 MW Karnali Chisapani project in performance to generate electricity at extremely low cost on a massive scale. It can be roughly said that the 4180 MW Upper Karnali project might be able to produce as much as 50% of the total energy generated by the 10,800 MW Karnali Chisapani project at only about 1/3 cost of the latter.
The overwhelming superiority of the 4180 MW Upper Karnali storage project among the large hydropower projects identified so far in Nepal is so obvious that the team of the consultants conducting the pre-feasibility study of the 300 MW Upper Karnali project under the financial assistance of the World Bank found themselves duty bound to warn us to refrain from harming the 4180 MW Upper Karnali storage project. They have clearly stated in the pre-feasibility report that the construction of the 300 MW Upper Karnali project will preclude the implementation of the 4180 MW Upper Karnali storage project.
Is Parliamentary Committee Adequately Informed?
It is reported in the newspaper that at some stage the Parliamentary Natural Resources and Means Committee was also involved. It is not clear whether or not the Parliamentary Committee was informed about the fact that the 300 MW Upper Karnali project and the mammoth 4180 MW Upper Karnali storage project are mutually exclusive. Do all the members of the Parliamentary Committee know the whole truth about the Upper Karnali projects? Is the Acharya task force or another Committee under the former finance secretary, set up to advise the Government, competent to make satisfactory recommendation, which requires in-depth analysis of all relevant technical documents? .People Must be Informed
There is no escaping the fact it is not possible to implement the proposed 300 MW Upper Karnali project without sacrificing the most attractive 4180 MW Upper Karnali storage project. Do not the people of our country have the right to know from the Water Resources Ministry and Parliamentary Natural Resources and Means Committee why the mammoth 4180 MW Upper Karnali storage project is being sacrificed to implement the relatively tiny 300 Upper Karnali project?Why Upper Karnali Storage So Attractive
The Karnali river makes a big loop in its lower reach near a place called Asare. From here the river flows in the south-east direction for about 25 kilometers, after that the river makes a complete reversal in its direction. The river comes back to a point just two kilometers away from its earlier position near Asare. There is a drop of about 150 meters in Karnali river bed elevations between these two positions merely two kilometers away from one another The project to utilize this bend for power generation is known as the Upper Karnali Project. . There are very good sites to build a large storage dam at the beginning of the bend. Thus, it makes the Upper Karnali Storage Project far superior to the 10,800 MW Karnali Chisapani Project in terms of per unit capacity investment cost because its hydropower station would be operating at a firm head two times greater than that of the latter though the total length of the waterway of both these hydropower plants would be almost exactly the same.Large Cost Reduction at Higher Heads
Of all the site characteristics, head is the most important. Design guidelines, 1989 approved by the American Society of Civil Engineers ( a document used throughout the world for the design of hydropower) has given some simple reasoning that would help to explain why the Upper Karnali project operating at a head about two times greater by comparison with the Chisapani hydropower could be built at far less per unit installed capacity cost. "Very simply if one doubles the head the quantity of water needed to produce a certain amount of energy is halved, Thus, for like site energy development the conduit area and reservoir volume are halved and further large cost reductions occur for powerhouse and machinery costs. This fundamental consideration is at the root of the large cost reductions that occur at higher heads." Needless to mention that the lower investment cost means the generation cost of the electricity would also be less.Comparative Investment Cost of Upper Karnali Storage
By comparison with the mammoth 10,800 MW Karnali Chisapani Project the firm head of the Upper Karnali Storage Project would be almost two times greater. It can be derived based on Stage A Optimization Study Data of the World Bank financed Karnali Project (Chisapani) Study report that per KW installed capacity construction cost of the Upper Karnali Storage Project could be only about 2/3 of such cost of the project at Chisapani. If such comparative cost reduction advantage is treated as additional bonus to accrue to Nepal on top of normal royalty to be received from private developer then our country might be able to earn per year at present cost of peaking energy about US $ 300 million as extra bonus which is equivalent to gross value of the total annual production of paddy in the whole country considered to be between 2.5 to 3 million tons at a price of about US $ 100 per ton.Upper Karnali Pre-feasibility Report
The World Bank supported pre-feasibility study has clearly explained that the 4180 MW Upper Karnali Storage Project and the 300 MW Upper Karnali Diversion Project are mutually exclusive. The relevant excerpt from the World Bank supported study report is presented below.
“Even when assuming that the KR 1 A run-of-river project (it indicates the small 300 MW Upper Karnali project) is a sunk cost, it will be seen that a single large power plant (4180 MW) associated with the major storage project is less costly than the combined cost of smaller plant at the same location (3532 MW) and a second power plant at the foot of the storage dam ( 348 MW) discharging directly into the KR 1A run-of-river project head pond. Based on this assessment, it appears that the later development of the major hydro storage project at Site KR 1 ( 4180 MW Upper Karnali Storage Project) would cause the KR 1A run-of-river project to be effectively discontinued. There may be limited opportunity for secondary energy generation during the periods of spillageâ€.Foreign Expert Against 300 MW Upper Karnali
Mr. Paul Terrell from the Bechtel International of the USA was Chief Advisor Consultant of the Upper Karnali Project study conducted under the World Bank financial assistance. Mr. Paul Terrell has categorically cautioned Nepal in his article published in the journal “HIMAL†that our country should never compromise optimum development for the sake of a quick deal.In Conclusion
Our grandiose national plans to develop our water resources to uplift the economic condition of our country in general and the people of Karnali in particular would be nothing more than an empty rhetoric if we failed to intervene in time to save the 4180 MW Upper Karnali Storage Project which might be the best even in the whole world for the generation of cheap peaking energy on a large scale. We should not hesitate to invite competent foreign experts for advice if we find ourselves not capable to make correct judgment on this very important matter.